Rulemaking Relating to Reliability Must-Run Service

Summary

This rulemaking will amend certain aspects of PUC Subst. R. §25.502, including the notification requirements applicable to generation resources and ERCOT's evaluation of the need for RMR contracts. Other existing rules may be amended and new rules may be established as necessary.

Staff Assigned

Julia Harvey
Competitive Markets Division
julia.harvey@puc.texas.gov
512-936-7371

Mark Bryant
Competitive Markets Division
mark.bryant@puc.texas.gov
512-936-7279

John Poole
Infrastructure and Reliability Division
john.poole@puc.texas.gov
512-936-7162

Project Schedule

The adopted rule will be published in the Texas Register on October 13, 2017 and effective on January 1, 2018.

Documents Available

Order Adopting Amendments to §25.502 as Approved at the September 28, 2017 Open Meeting
Proprosal for Publication of Amendment to §25.502 as Approved at the March 30, 2017 Open Meeting
Strawman
Second Strawman
Initial Rulemaking Planner and Timeline