Facility Name: |
Baytown Energy Center LLC |
Type: |
Other |
County: |
Harris |
Control Area: |
ERCOT |
Capacity (MW): |
590.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
CENTERPOINT ENERGY HOUSTON ELECTRIC LLC |
|
Facility Name: |
BOSQUE POWER PLANT |
Type: |
Other |
County: |
Unknown |
Control Area: |
ERCOT |
Capacity (MW): |
802.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
TEXAS-NEW MEXICO POWER COMPANY |
|
Facility Name: |
Calpine Hidalgo Energy Center, L.P. |
Type: |
Other |
County: |
Hidalgo |
Control Area: |
ERCOT |
Capacity (MW): |
456.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
AEP TEXAS CENTRAL |
|
Facility Name: |
Channel Energy Center, LLC |
Type: |
Other |
County: |
Harris |
Control Area: |
ERCOT |
Capacity (MW): |
467.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
CENTERPOINT ENERGY HOUSTON ELECTRIC LLC |
|
Facility Name: |
Corpus Christi Cogeneration, LLC |
Type: |
Other |
County: |
Nueces |
Control Area: |
ERCOT |
Capacity (MW): |
406.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
AEP TEXAS CENTRAL |
|
Facility Name: |
DEER PARK ENERGY CENTER LLC |
Type: |
Other |
County: |
Harris |
Control Area: |
ERCOT |
Capacity (MW): |
1021.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
CENTERPOINT ENERGY HOUSTON ELECTRIC LLC |
|
Facility Name: |
Freestone Power Generation, LLC |
Type: |
Other |
County: |
Freestone |
Control Area: |
ERCOT |
Capacity (MW): |
953.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
ONCOR ELECTRIC DELIVERY COMPANY |
|
Facility Name: |
GUADALUPE POWER PARTNERS LP |
Type: |
Other |
County: |
Guadalupe |
Control Area: |
ERCOT |
Capacity (MW): |
1050.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
GUADALUPE VALLEY ELECTRIC COOPERATIVE INC |
|
Facility Name: |
JACK A. FUSCO ENERGY CENTER LLC |
Type: |
Other |
County: |
Fort Bend |
Control Area: |
ERCOT |
Capacity (MW): |
593.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
CENTERPOINT ENERGY HOUSTON ELECTRIC LLC |
|
Facility Name: |
MAGIC VALLEY GENERATING STATION |
Type: |
Other |
County: |
Hidalgo |
Control Area: |
ERCOT |
Capacity (MW): |
668.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
AEP TEXAS NORTH |
|
Facility Name: |
Pasadena Cogeneration, L.P. |
Type: |
Other |
County: |
Harris |
Control Area: |
ERCOT |
Capacity (MW): |
664.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
CENTERPOINT ENERGY HOUSTON ELECTRIC LLC |
|
Facility Name: |
Texas City Cogeneration, LLC |
Type: |
Other |
County: |
Galveston |
Control Area: |
ERCOT |
Capacity (MW): |
410.00 |
Non Renewable Fuels: |
|
Renewable Energy Credit Date: |
|
Service Area: |
CENTERPOINT ENERGY HOUSTON ELECTRIC LLC |
|
23495 Type: DOCKET Open Date: 12/29/2000 Close Date: 1/23/2001 Filings: New Note: PGC Application
|
23495-04 Type: DOCKET Open Date: 5/10/2001 Close Date: 5/15/2001 Filings: Facilities Change Note: AMENDMENT - Add the Generating Facility - Calpine/Gentex Lost Pines, L.P. 500 MW in Bastrop County under ERCOT and LCRA.
|
23495-06 Type: DOCKET Open Date: 9/13/2001 Close Date: 9/26/2001 Filings: Facilities Change Note: AMENDMENT - Adding Generating Facility - Channel Energy Center, L.P. 190 MW in Harris County as part of ERCOT in Reliant/HL&P area.
|
23495-09 Type: DOCKET Open Date: 10/30/2001 Close Date: 11/5/2001 Filings: Facilities Change Note: AMENDMENT - Add Generating Facilities - Calpine Magic
Valley Energy Center Project - 720 MW in Hidalgo County as part of ERCOT in AEP service area.
|
23495-12 Type: DOCKET Open Date: 8/7/2002 Close Date: 8/29/2002 Filings: Facilities Change Note: AMENDMENT - Consolidation of Docket nos. 26134, 26294, 26295 and 26296 into 23495. Addition of Generating Facilities: Corpus Christi Cogeneration, L.P. 540 MW, Baytown Energy Center, L.P. 709 MW, Channel Energy Center, L.P. 531 MW and Freestone Power Generation, L.P. 1030 MW.
|
23495-15 Type: DOCKET Open Date: 11/8/2002 Close Date: 1/8/2003 Filings: Facilities Change Note: AMENDMENT - Addition of Generating Facilities - Deer Park Energy Center Limited Partnership - 950 MW - in Harris County as part of ERCOT in Reliant Service Area.
|
23495-18 Type: DOCKET Open Date: 8/6/2003 Close Date: 8/8/2003 Filings: Facilities Change Note: AMENDMENT - REMOVAL of Generating Facilities - Calpine Magic Valley Energy Center Project and Calping/Gentex Lost Pines, L.P.
|
23495-21 Type: DOCKET Open Date: 3/31/2005 Close Date: 10/30/2008 Filings: Facilities Change Note: AMENDMENT - Addition of Generating Facilities - Deer Park Energy Center Limited Partnership.
|
26294 Type: DOCKET Open Date: 7/18/2002 Close Date: 8/29/2002 Filings: Facilities Change Note: AMENDMENT - Consolidated Docket No. 26294 into 23495-12 - Adding Generating Facility: Baytown Energy Center, L.P. - 709 MW in Chambers County as part of ERCOT in Reliant Service Area.
|
26295 Type: DOCKET Open Date: 7/18/2002 Close Date: 8/29/2002 Filings: Facilities Change Note: AMENDMENT - Consolidated Docket No. 26295 into 23495-12 - Adding Generating Facility: Channel Energy Center, L.P. - 531 MW in Harris County as part of ERCOT in Reliant Service Area.
|
26296 Type: DOCKET Open Date: 7/18/2002 Close Date: 8/29/2002 Filings: Facilities Change Note: AMENDMENT - Consolidated Docket No. 26296 into 23495-12 - Adding Generating Facility: Freestone Power Generation, L.P. - 1030 MW in Freestone County as part of ERCOT in Luminant Service Area.
|
26840-245 Type: NOTIFICATION Open Date: 12/19/2009 Close Date: 12/19/2009 Filings: Notification, Contact List Note: Notification of business address change and change of contact
|
37081-19 Type: NOTIFICATION Open Date: 12/13/2010 Close Date: 12/13/2010 Filings: Notification Note: Notification of change in percentage of ownership - 25% interest in the assets of Freeston Energy Center sold to Rayburn Country Electric Coop, Inc.
|
37925 Type: DOCKET Open Date: 1/29/2010 Close Date: 2/8/2010 Filings: Facilities Change, Name Change Note: APPLICATION TO AMEND FACILITY NAME - DEER PARK ENERGY CENTER LP TO DEER PARK ENERGY CENTER LLC
|
39858 Type: PROJECT Open Date: 10/20/2011 Close Date: 10/26/2011 Filings: Facilities Change Note: AMENDMENT TO UPDATE FACILITIES
|
40938 Type: PROJECT Open Date: 11/7/2012 Close Date: 11/15/2012 Filings: Facilities Change Note: PGC AMENDMENT TO ADD THE BOSQUE POWER FACILITY
|
42318 Type: PROJECT Open Date: 3/19/2014 Close Date: 4/2/2014 Filings: Facilities Change, Relinquishment Note: PGC AMENDMENT - ACQUISITION OF GUADALUPE POWER PARTNERS, LP
|
47336 Type: PM Open Date: 6/20/2017 Close Date: 6/30/2017 Filings: Facilities Change Note: PGC AMENDMENT APPLICATION
|
47902 Type: PROJECT Open Date: 12/27/2017 Close Date: 1/26/2018 Filings: Other Note: AMENDMENT TO PGC - UPDATE NAME CHANGE IN FACILITY FROM BRAZOS VALLEY ENERGY LLC
TO
JACK A, FUSCO ENERGY CENTER LLC
|
48184 Type: PROJECT Open Date: 4/18/2018 Close Date: 4/18/2018 Filings: Change in Ownership/Control Note: AMENDMENT TO PGC - UPDATE CHANGE IN OWNERSHIP/CONTROL AND AFFILIATES.
|
51347 Type: PROJECT Open Date: 9/17/2020 Close Date: 10/15/2020 Filings: Other Note: AMENDMENT TO PGC - UPDATE CHANGE IN AFFILIATES
|
51553 Type: PROJECT Open Date: 11/24/2020 Close Date: 12/18/2020 Filings: Other Note: AMENDMENT TO PGC - UPDATE CHANGE IN AFFILIATES
|
55749-176 Type: PROJECT Open Date: 2/28/2024 Close Date: 2/28/2024 Filings: Renewal Note: EVEN NUMBERED PGC RE-REGISTRATION 2024
|
56258 Type: PROJECT Open Date: 2/23/2024 Close Date: 3/8/2024 Filings: Other Note: AMENDMENT TO PGC - UPDATE AFFILIATES
|
57185 Type: PROJECT Open Date: 10/9/2024 Close Date: 10/24/2024 Filings: Other Note: PGC REGISTRATION AMENDMENT - AFFILIATES LIST UPDATE
| |