DECORDOVA BESS LLC
20753
Type: |
Power Generator |
Registration Date: |
7/12/2023 |
|
No DBA Records
Facility Name: |
DeCordova Battery Energy Storage System (BESS) |
Type: |
Other |
County: |
Hood |
Control Area: |
ERCOT |
Capacity (MW): |
263.00 |
Non Renewable Fuels: |
Battery Storage facility |
Renewable Energy Credit Date: |
|
Service Area: |
ONCOR ELECTRIC DELIVERY COMPANY |
| |
Company / Physical (Mailing Address) DECORDOVA BESS LLC NED BONSKOWSKI VICE PRESIDENT TEXAS REGULATORY POLICY 1005 CONGRESS AVE SUITE 750 AUSTIN ,TX 78701 Email: ned.bonskowski@vistracorp.comPhone: 512-349-6464
|
Regulatory Rep DECORDOVA BESS LLC NED BONSKOWSKI VICE PRESIDENT TEXAS REGULATORY POLICY 1005 CONGRESS AVE SUITE 750 AUSTIN ,TX 78701 Email: ned.bonskowski@vistracorp.comPhone: 512-349-6464
|
Regulatory Rep (Primary Emergency) DECORDOVA BESS LLC NED BONSKOWSKI VICE PRESIDENT TEXAS REGULATORY POLICY 1005 CONGRESS AVE SUITE 750 AUSTIN ,TX 78701 Email: ned.bonskowski@vistracorp.comPhone: 512-349-6464
| |
No Registration/Annual Report Records
Docket/Project/Control Numbers |
|
55138 Type: PROJECT Open Date: 6/12/2023 Close Date: 7/12/2023 Filings: New Note: PGC REGISTRATION APPLICATION
|
55349 Type: PROJECT Open Date: 8/11/2023 Close Date: 9/12/2023 Filings: Other Note: AMENDMENT TO PGC - UPDATE CHANGE IN new intermediate parent
companies due to internal corporate restructuring.
|
End Report